From wafer to delivery: why lead times can suddenly increase
You may have experienced it yourself: a component with a six-week lead time suddenly increasing to twelve, twenty or even thirty weeks within a matter of months. Not because something went wrong, but simply because demand increased. So how can lead times rise that quickly?
In our previous article, we discussed the developments surrounding Nexperia. However, sudden increases in demand can have many different causes. In recent months, the rapid growth of AI has significantly increased demand for memory components. At the same time, geopolitical tensions, such as developments around Iran or trade restrictions between global powers, can disrupt export flows and drive regions to secure inventory. And sometimes the cause is much simpler: a recovering market, a successful product launch or a customer experiencing rapid growth in orders. All of these situations have one thing in common: demand increases, and the supply chain has to absorb the impact.
A long and layered production process
A chip literally starts with sand. This is transformed into silicon, then into a raw wafer, before moving through multiple complex production stages until the component is tested, packaged and ready for delivery.
Wafer fabrication alone can take anywhere from eight to twenty-eight weeks. Wafer testing, assembly and final testing add another four to ten weeks to the process. As a result, total lead times can range from twelve to thirty-five weeks, depending on the type of component.
Between each of these stages, buffer stocks are maintained to keep the process moving efficiently. Under normal circumstances, these buffers ensure that each production step has sufficient material available and that lead times remain manageable.
Why lead times increase in jumps, not gradually
As demand increases, these buffers are depleted faster than they can be replenished. This happens step by step. First, distributor stock runs out. Then assembly stock. Then tested wafers. Every depleted buffer pushes lead times one step further back into the supply chain.
And replenishing those buffers takes time — a lot of time. The process starts again at wafer level, and that cycle takes months. Production capacity at semiconductor manufacturers is planned years in advance and cannot be scaled up quickly. As a result, lead times do not increase gradually, they jump. From six to twelve weeks. From twelve to twenty. From twenty to thirty, until you are waiting for capacity that has yet to be scheduled.
Practical example: from 16 to 26 weeks
Imagine ordering a microcontroller today. Assembly stock is still available, resulting in a lead time of 16 weeks.
One month later, a colleague orders the same component. The assembly stock has been depleted, meaning the back-end process needs to restart, adding another 6 weeks. The lead time now increases to 22 weeks.
Another month later, the wafer stock is also exhausted. The fab needs to restart production, adding another 12 to 20 weeks in the front-end process. Suddenly, the lead time jumps to 26 weeks or more.
Nothing about the component itself has changed. The only difference is that the buffer stock has disappeared.
What can you do?
The supply chain is long and has limited flexibility to respond quickly. However, there are ways to prepare for this proactively. Sharing a forecast, even if it is not fully accurate, can make a significant difference. It allows suppliers throughout the chain to reserve capacity well before shortages become visible. This remains one of the most effective ways to improve supply continuity. If forecasting is challenging due to your market dynamics or customer situation, it is advisable to analyse the long lead time items within your BOM together with your account manager. Mach uses dedicated tooling to identify and analyse these critical components.
Based on these insights, a tailored action plan can be created to secure critical parts in time — often with minimal risk until shortly before delivery. By making clear agreements with suppliers, flexibility is maintained while capacity and materials can already be prepared in advance. These agreements are managed and monitored through our tooling, helping you avoid surprises during ramp-ups or periods of rapid growth.
Feel free to contact your account manager for a complimentary long lead time analysis of your BOM. Together, we help you stay ahead when the market shifts.